Al Maktoum International Airport construction explained

A plain guide to Dubai's new airport build: who runs it, what has been awarded, the West Terminal, contractors named so far, transport links and the 2032 target.

UAE Industry Insider NewsroomPublished 28 November 20263 min read

Al Maktoum International Airport (DWC) at Dubai South is the largest construction programme in the UAE. This guide explains how the project is organised, what has been awarded so far and what comes next. It uses only official statements and named news reports.

The project in brief

At full build-out, the airport is planned to have five parallel runways, 430 aircraft gates and capacity for 260 million passengers and 12 million tonnes of cargo a year, bne IntelliNews reported. It described the first phase as part of a $35 billion plan.

The National reported that the first phase is due to open in 2032, and that Dubai International and DWC will run in parallel during the transition.

bne IntelliNews also reported that Coop Himmelb(l)au and Dar Al-Handasah were confirmed in 2024 as lead master planning and design consultants.

Who runs it

Dubai Aviation Engineering Projects (DAEP) manages the programme. The Dubai Media Office said DAEP is responsible for planning, design, procurement, construction and operational readiness. It sets the order of contract packages, manages technical interfaces and monitors quality, safety, cost and schedule.

Contracts awarded so far

The Dubai Media Office set out the award history in November 2026:

  • Earlier phase: about AED23.815 billion covering enabling works, substructure packages, the automated people mover and the baggage handling system.
  • November 2026: about AED56.5 billion of new awards.
  • Total to date: about AED80 billion.

The November awards cover substructure and underground works for the West Terminal Building, Concourse 1 and Concourse 4; superstructure, roof spaceframes and building systems for Concourses 2 and 3; and two principal 132/11 kV substations.

Contractors named in reports

The November announcement did not list contractors. Earlier reports named some of them:

  • West Terminal substructure: in October 2026, MEP Middle East and bne IntelliNews, citing MEED, reported that a joint venture of China Civil Engineering Construction Corporation (CCECC) and Abu Dhabi-based Tristar Engineering & Construction won an estimated AED10 billion package. The West Terminal substructure is among the packages listed in the November announcement.
  • Automated people mover: IndexBox, citing MEED, reported that a joint venture of Mitsubishi Corporation and Larsen & Toubro won an estimated $1.5 billion contract covering four underground stations in the first phase.

The West Terminal

MEP Middle East reported that the West Terminal will be a seven-level building of 800,000 square metres, designed for 45 million passengers a year. It is the second of three planned terminals. The substructure scope includes foundations, basement walls, columns, slabs, apron slabs and tunnels.

Progress on site

As of November 2026, the Dubai Media Office reported:

  • More than 24.23 million cubic metres excavated
  • More than 7,635 piles completed
  • More than 875,603 cubic metres of concrete and 226,270 tonnes of reinforcement steel placed on the Concourse 2 and 3 substructures
  • About 14,000 people working across the packages

Transport links

The Arabian Post reported that Dubai's Executive Council approved an extension of the Dubai Metro to the Al Maktoum International Airport area on 10 November 2026. Khaleej Times has reported that metro services to the airport are due to begin in 2031. The Arabian Post also said the West Terminal is planned to connect with airport express services and Etihad Rail's high-speed network.

What is still to come

Aviation-focused reports point to more packages for terminal superstructures, façades and roofing, airfield works and utilities. bne IntelliNews noted that most contracts by value were still to be let when the West Terminal substructure was awarded.

What it means for businesses

  • Tier-two contractors can expect subcontract opportunities in MEP, façades, steelwork, fit-out and specialist airport systems.
  • Suppliers of concrete, steel, cables, switchgear and cooling equipment face long-term demand.
  • Service firms in labour accommodation, transport, catering and safety support a large site workforce.

This guide is general information only and is not investment advice. Figures are as reported by the sources listed.

Topics:Al Maktoum International AirportDWCDubai Aviation Engineering Projectsairport constructionWest TerminalDubai Metromegaprojects

Sources & References

Frequently Asked Questions

When will Al Maktoum International Airport open?
The first phase is due to open in 2032, according to The National, citing Dubai Airports.
Who manages the construction programme?
Dubai Aviation Engineering Projects manages planning, procurement, construction and operational readiness for the airport.
How big will the finished airport be?
bne IntelliNews reported that at full build-out the airport is planned to have five parallel runways, 430 aircraft gates and capacity for 260 million passengers and 12 million tonnes of cargo a year.
How can my company work on the project?
Main packages are procured by Dubai Aviation Engineering Projects. Most suppliers and specialist firms will work through the main contractors, so following award announcements and contacting named contractors is the usual route.

Commercial Publishing & PR

Publish your press release in Construction & Infrastructure

Reach executives, partners, and decision-makers following UAE Construction & Infrastructure with a permanent, indexed corporate announcement.

More in Construction & Infrastructure