How to license a clinic in Dubai in 2026: the DHA Sheryan process explained

A step-by-step guide to the Dubai Health Authority's two-stage facility licensing process on Sheryan, from initial approval to activation, with sourced requirements.

UAE Industry Insider NewsroomPublished 28 November 20263 min read

Dubai had 5,931 licensed healthcare facilities in the first half of 2026, up about 7% on a year earlier, Arabian Business reported. Every one of them on the mainland went through the Dubai Health Authority's (DHA) licensing process. Here is how it works.

Who this applies to

This guide covers health facilities on the Dubai mainland, licensed by the DHA. Facilities in Dubai Healthcare City are overseen by a separate free zone authority. Abu Dhabi facilities are licensed by the Department of Health – Abu Dhabi.

The two stages

According to the DHA's facility licensing manual, a health facility must complete two services to get a licence:

StageSheryan serviceResult
1New Facility LicenseInitial approval and a licence with inactive status
2Activate Facility LicenseThe inactive licence becomes active, allowing the facility to operate

All applications go through Sheryan, the DHA's online licensing system. Manual or emailed applications are not accepted.

Stage 1: New Facility License

The DHA manual says a new facility licence can be started with the DHA itself, or through a trade licence authority such as the Department of Economy and Tourism (DET) or a free zone authority. The owner or an authorised person registers through Sheryan or the Invest in Dubai platform.

According to the DHA's service page, the steps are:

  1. Log in and select the New Healthcare Facility License service.
  2. Fill in and submit the online application, including a facility proposal.
  3. Pay the required fees.
  4. Receive an application reference number.
  5. The DHA reviews the request.
  6. Approved requests are issued with an inactive facility licence.

Prerequisites listed by the DHA:

  • Getting a trade licence before this step is optional.
  • The facility needs an electronic medical record that complies with the NABIDH minimum data set and standards.

Pabau, citing DHA fees, reports that initial approval for a clinic costs AED1,000 and that the DHA quotes five working days. Fees vary by facility type, so check the current schedule on Sheryan.

Between the stages

After initial approval, the facility is designed, fitted out and staffed. Points to plan for:

  • Floor plan: Ozanix Partners notes that the plan should be prepared by a DHA prequalified facility design consultant, following the DHA Health Facility Guidelines.
  • Radiation equipment: The DHA manual says facilities that install X-ray equipment need initial registration with the Federal Authority for Nuclear Regulation (FANR).
  • Trade licence: A valid trade licence is needed before activation.
  • Medical Director: The manual lists appointing a Medical Director as a requirement.
  • Staff licences: Clinical staff need their own DHA professional licences.

Stage 2: Activate Facility License

When the clinic is built, equipped and staffed, the facility submits the Activate Facility License service on Sheryan. The DHA inspects the facility. Once approved, the licence becomes active and the clinic can treat patients.

Ozanix Partners notes that confirmation of tested NABIDH connectivity is part of this stage. The firm also says the DHA treats licensing fees as non-refundable except with exceptional approval.

Common mistakes to avoid

  • Starting fit-out before approvals. Build only after layouts are approved.
  • Ignoring NABIDH early. An EMR that cannot connect to NABIDH can delay activation.
  • Hiring before checking licence eligibility. Clinicians must qualify for DHA professional licences.
  • Choosing the wrong jurisdiction. Mainland, free zone and Abu Dhabi rules differ.

Quick checklist

  • Sheryan account created
  • Facility proposal ready
  • NABIDH-compliant EMR selected
  • Initial approval (inactive licence) received
  • Trade licence obtained
  • Medical Director appointed
  • Approved layout and fit-out completed
  • FANR registration if using X-ray
  • Staff licensed
  • Activation and inspection passed

This guide is general information, not legal or regulatory advice. Requirements and fees change. Always confirm the current rules on the DHA's Sheryan portal before applying.

Topics:clinic licence DubaiDHA licensingSheryanhealthcare business setupNABIDHDubai clinics

Sources & References

Frequently Asked Questions

How many stages are there in DHA facility licensing?
Two. The New Facility License service gives an inactive licence. The Activate Facility License service turns it into an active licence once the facility is ready and inspected.
Do I need a trade licence before applying to the DHA?
The DHA's New Facility License service page lists obtaining a trade licence first as optional. A valid trade licence is needed later in the process.
What is NABIDH?
NABIDH is Dubai's health information exchange. The DHA requires an electronic medical record that complies with NABIDH standards.
How long does it take?
It depends on the facility. Pabau, citing the DHA, says initial approval for a clinic is quoted at five working days. Fit-out, staffing and inspection take longer.

Commercial Publishing & PR

Publish your press release in Healthcare & Life Sciences

Reach executives, partners, and decision-makers following UAE Healthcare & Life Sciences with a permanent, indexed corporate announcement.

More in Healthcare & Life Sciences